Navigation:  Basic Working Procedures > Service Agreements > Display the Agreement Screen >

Summary Tab

Previous pageReturn to chapter overviewNext page

The Summary Tab displays Profit and Loss information taken from Work Orders and Invoices related to this Agreement.

Here is a sample Summary Tab screen. The lines are numbered to match the explanations and other screen samples below.

 

1.Work Orders Cost - matches Actual Cost on 5 Work Orders to-date
2.Work Orders Overhead - matches Actual Overhead on 5 Work Orders to-date
3.Work Orders Sale Amount - matches Billed Amount on 5 Work Orders to-date
4.Agreement Amount - matches the original Agreement Amount on the General Tab
5.Agreement Billed Amount - so far no billings directly against the Agreement Amount
6.Total Work Orders Cost Amount - matches Actual Cost on 5 Work Orders to-date
7.Total Sale Amount - the projected Total Sale Amount by the end of the contract. Combines the non-Agreement and Agreement Amount on Work Orders related to this Agreement
8.Net Profit Amount - the projected result of the Total Sale Amount minus the Total Cost of Work Orders entered to-date under the contract (note, based on Work Orders to-date)
9.Profit Percent - the projected Net Profit Amount divided by the Total Sale Amount (using billings to-date)
10.Total Sale Amount to Date - the to-date Total Sale Amount. Combines the non-Agreement and Agreement Amount on Work Orders so far.
11.Net Profit Amount to Date - the to-date result of the Total Sale Amount minus the Total Cost of Work Orders entered to-date under the contract
12.Profit Percent to Date - the to-date Net Profit Amount divided by the Total Sale Amount

Here is the matching Work Orders screen, with numbers that tie to the Summary Screen:

Here is the matching Invoices screen, with numbers that tie to the Summary Screen:

 


Page url: http://www.fieldone.com/startech/help/index.html?_agreement_screen_summary_tab_.htm