The step to Complete a Schedule Slot is optional, but may be convenient when different staff members are using Schedule Board information.
• | For instance, the Technician out in the field can use Completed Status to inform office staff that assigned work is finished. |
• | Or again, if Posting is not done daily, office staff may wish to use the Completed Status to mark Schedule Slots that are ready for some other person to Post. |
There are several ways to change a Schedule Slot to Completed Status:
► | Just right-click on a Schedule Slot and simply choose the Status for Completed |
► | Or, use the Actions button on the lower left of the Schedule Board |
2. | Click on the Actions button, then select Complete Schedule Slots |
3. | Press Yes for the confirmation message that appears |
► | Or, you can double-click to open the Schedule Slot Details and change the Status to Completed in the Status select-box. |
► | Then click to select a Schedule Slot and click on Complete Slot button on the bottom left. |
► | Select the Schedule Slot detail line you would like to complete. |
► | Use the select-box in the detail line to change the Status to Completed |
Please Note:
A Completed Schedule Slot will have the color Gray on the Schedule Board.
Page url: http://www.fieldone.com/startech/help/index.html?_sched_slot_tasks_complete_a_schedule_slot_.htm